As a result of a staff/contractor miscommunication an incorrect cost estimate for the "South Bowl" loop trail was included in the City Council memo. The estimated cost was reported as $350,000 while the actual cost estimate is $160,000 for trail construction plus an additional + $100,000 for bridging a drainage should the trail be constructed.
If there are any questions regarding this matter please call Mike Patton or Jim Reeder at (303) 441-3440